UFC 1-300-09N
25 May 2005
Change 1, 22 February 2006
Change 2, 4 December 2006
10-5
FINAL DESIGN SUBMITTALS.
The Final Submittal provides a complete and final set of contract documents ready for
bid solicitation by the Government, or in the case of Design-Build, ready for construction
by the Contractor. All previous government review comments must have been
addressed.
Unless specified otherwise by the Contract, provide final submittals in electronic format
in accordance with Chapter 7.
Provide the following, as a minimum, for the Final Submittal:
10-5.1
Basis of Design.
Submit final, revised and updated, Basis of Design as required herein and by the
Discipline-Specific UFCs.
10-5.1.1
Sustainable Design.
In addition, for Design-Build projects, update information including sustainable design
validation and certification information required by UFGS Section 01 33 10.05 20
(01331) of the project RFP.
10-5.2
Drawings.
Provide complete construction drawings (detailed in the PreFinal Design Phase)
organized by discipline in accordance with this UFC and Discipline-Specific UFCs.
Ensure NAVFAC drawing numbers are entered into the appropriate location on the
NAVFAC standard drawing border.
10-5.2.1
Shop Drawings.
For Design-Build projects, follow the requirements of the RFP when shop drawings are
used as design drawings.
10-5.3
Specifications or RFP.
Provide complete, final specifications or RFP with redlines executed. Organize and
compile the package as detailed in Chapter 3 or Chapter 5.
10-5.3.1
Environmental Specifications.
Comply with additional requirements in UFC 3-800-10N, for Environmental
specifications.
64