Provide a bound copy of the computerized energy analysis that includes input and
output data in their entirety.
10-3.5.3.2
Life Cycle Cost Analysis.
Submit the computerized LCC analysis utilizing the latest edition of the NIST Building
Life-Cycle Cost Program.
10-3.5.3.3
Provide a bound copy of the computerized load calculations with input and output data
in their entirety.
10-3.5.3.4
ASHRAE 90.1 Compliance Calculations.
Submit calculations and compliance forms indicated in the Basis of Design.
10-3.5.4
Electrical.
Updated Design Analysis to substantiate design level shown. Provide calculations
including:
Lighting: Interior and Exterior Foot-candles.
Load Analysis.
Service size.
Feeder size.
Larger special circuit sizes.
10-3.5.5
Fire Protection.
Submit all calculations supporting all fire suppression and fire alarm/detection systems
for the project. Calculations for systems, features, or elements other than fire
suppression or detection will be required as applicable. Fire suppression system
calculations must be prepared using commercially available computer software.
10-3.6
Environmental Report.
For Design-Bid-Build projects, provide reports as required in UFC 3-800-10N.
10-4
PRE-FINAL DESIGN SUBMITTALS (100%).
The intent of the Pre-Final submittal is to provide a complete set of drawings and
specifications. The following are the minimum requirements of a Pre-Final submittal:
60