UFC 1-300-09N
25 May 2005
Change 1, 22 February 2006
Change 2, 4 December 2006
10-5.3.2
Design-Build Design Submittals.
For Design-Build projects, follow the requirements of the RFP when manufacturer's
catalog data is used in lieu of prescriptive specifications.
10-5.3.2.1
Fire Protection Specifications.
For Fire Protection systems only, provide manufacturer's data sheets instead of
prescriptive specifications, for the suppression systems, the detection and alarm
systems, firestopping, and spray-applied fireproofing. In exception, and in addition,
submit prescriptive specifications for Fire Protection systems when provided in the RFP.
10-5.4
Project Information Form.
Provide a final, completed PIF for the project for Design-Build RFP Development and for
Design-Bid-Build submittal.
10-5.5
Color Documentation Binders.
Provide separate interior and exterior color documentation binders indicating all
proposed material and color selections.
10-5.6
Calculations.
Revise design analysis and calculations as required to reflect resolution of all previous
government review comments and as required by the discipline-specific UFCs.
10-5.7
Additional Overseas Submittals Requirements.
Provide the following:
Host Nation Life Safety and Building Code analysis.
Comparisons of Host Nation requirements with NFPA Codes and UFC 1-
200-01.
Translate the Geotechnical Report into English. Unless stated otherwise in the contract,
the boring logs shall be shown in two languages, English and the local language of
country of bidding and construction.
65