UFC 1 -300-08
30 JUNE 2004
the pre-design meeting)
6-2.2.7
List of Installed Building Equipment (IBE) with models and serial numbers
and warranty information
6-2.2.8
List of Equipment in Place (EIP) with models and serial numbers and
warranty information provided
6-2.2.9
Equipment operations and maintenance (O&M) manuals and systems
operating manuals
6-2.2.10
Test results of mechanical and electrical systems
6-2.2.11
Systems warranty information
6-2.2.12
Certified copies of pertinent real estate documents, such as deeds of
acquisition, leases or judgments from condemnation proceedings
6-2.2.13
Contract information (e.g., submittals and specifications)
6-2.2.14
Backup cost basis documentation such as records of payment see Section
6-6
6-2.2.15
Wiring diagrams
6-2.2.16
Piping layouts
6-2.2.17
Color codes for wiring and piping
6-2.2.18
Valve charts and tags
6-2.2.19
Spare parts catalogs
6-2.2.20
List of special handles and tools required
6-2.2.21
Properly tagged keys
6-3
COMPLETENESS STANDARDS.
Use the following standards as a
guide to
determine whether the DD Form 1354 is complete and should be signed, or possesses a
specific deficiency that would cause the accepting official not to sign and accept
accountability. These are guidelines for both the preparer as a self-check and the
accepting official. The exchange of a 1354 prior to date of transfer should allow sufficient
time for a review and feedback on any possible shortcomings to allow the preparer an
opportunity to "fix" the 1354 so it can be signed by both parties during the actual transfer.
6-2