Additive items shall be arranged such that the most essential portion of the work is
added first. Succeeding items are arranged in decreasing importance. During
evaluation of the offers, additive items are added to the base item in the order listed. As
each additive item is added, a new bid price is computed and compared to the available
funds. As additive items are determined to be within the funds available they are added
to the Contractor's bid price. If they are not within the funds available they are skipped.
Each additive item shall be independent of the others.