UFC 1-300-09N
25 May 2005
Change 1, 22 February 2006
Change 2, 4 December 2006
solicitation package. In exception, local procedures may require that the specification
writer prepare one or more of these sections, such as UFGS 00 01 15 (00102), List of
Drawings, and should be included in the specification package. When project includes
contract line items, provide UFGS 00 22 13 (00120), Supplementary Instructions to
Bidders, with the Project Information Form, but do not combine it with the other
specification sections in the final specification package.
5-6.3
Project Information Form (PIF).
Prepare and provide a Project Information Form (PIF) for Design-Bid-Build projects and
Development of RFP packages. The Government representative forwards the PIF to
the Contracting Specialist to prepare the Acquisition part of the solicitation. A
downloadable version of the PIF is available at http://www.wbdg.org/ccb under
Specifications Library - NAVFAC Specifications.
5-6.4
Format.
The format (e.g., page layout, size, and electronic format) for specifications is defined
by UFC 1-300-02. Print job headers with the job title, exactly as it appears on the
drawings, justified to the left, and with the eProjects Work Order Number or Maximo
Number justified to the right. For Prefinal submittals, follow the job title with "(Prefinal)."
5-6.5
General Requirements (Division 00 and 01) Specification Sections.
Edit the UFGS, General Requirements Sections, describing the general project
requirements for use in the project. Include any additional sections of a general
requirements nature, rather than of a technical nature, in General Requirements. For
Part 2, "General Requirements," of the six part Design-Build RFP, use the UFGS
sections shown in Part 2 of the Whole Building Design Guide, Navy Design-Build
master, as appropriate, listed and available at the following location:
www.wbdg.org/ndbm.
Typical General Requirements, UFGS sections used in a Design-Bid-Build project, as
applicable, include the following:
17