UFC 3-260-11FA
25 May 2005
SECTION 01016
DETAILED TECHNICAL REQUIREMENTS
FOR AIRFIELD DESIGN-BUILD
PART 1
GENERAL
1.1
INTRODUCTION
These RFP documents define the functional requirements of the
project. It is the Contractor's responsibility to further develop
the design, to prepare a proposal, and to provide a complete and
useable facility. The Contractor shall involve the Subcontractors
and Designers in the preparation of the proposal.
1.2
RFP TECHNICAL DOCUMENTS
The
RFP
drawings
and
specifications
should
be
used
as
complimentary documents. The requirements are intended to
complement one another and should not be viewed as independent
requirements that exclude or contradict the design as a whole.
The technical requirements in this RFP are the minimum standards
for quality of construction and materials. The drawings and
specifications are intended to allow the Contractor to choose
from a range of acceptable alternatives. However, deviations will
not be allowed from details included in the RFP documents such as
pavement dimensions, elevations, paving materials, or pavement
layer thicknesses. The Design-Build (D-B) Contractor shall
prepare drawings and specifications as required in Section 01012,
D-B Design After Award.
1.3
AIRFIELD DATA
1.3.1
Runway Type (Class)
1.4.1
Reference
UFC 3-260-01, Airfield Heliport Planning And Design, Attachment
15.
1.4.2
General Requirements
The following paragraphs describe the work included in each
construction phase, with the maximum time limit for completion of
the phase.
1.4.3
Drawings
01016 - 1