UFC 3-260-11FA
25 May 2005
The Contractor shall prepare a security/safety program that
includes the preparation and monitoring of site security and
operational safety.
1.7.2
Security
The Contractor shall prepare a plan for site security during
construction. The plan shall be submitted with the first design
submittal. The plan shall include detailed procedures for
controlling access to the project site through the use of gate
guards, ID badge, entry access lists and/or other measures as
required by the Air Base. The Contractor shall become acquainted
with all the required security measures of the Air Base during
the proposal phase.
1.7.3
Operational Safety
1.7.3.1
References
UFC 3-260-01,
Airfield
And
Heliport
Planning
And
Design,
Attachment 15
FAA ADVISORY CIRCULAR 150/5370-2E, Operational Safety On Airports
During Construction
1.7.3.2
Pre-Proposal Site Visit
Access to the airfield site and required security
clearance during the pre-proposal phase can be
detailed in Contract Clauses under PRE-PROPOSAL
CONFERENCE AND SITE VISIT. If this information is not
included in Contract Clauses, provide details in this
section. Information to be included consists of the
following:
When and where will the Pre-Proposal Conference be
held, if any?
Will individual site visits be allowed?
Will a site tour be conducted?
If so, at what
time?
Will pre-submittal of names and information of
conference/tour attendees be required? If so, how
many days in advance?
01016 - 3