TM 5-818-5/AFM 88-5, Chap 6/NAVFAC P-418
c. Steel sheet piling. Steel sheet pile cutoffs are con-
fill is required to ensure that the slurry is not trapped
structed employing the same general techniques as
within the backfill.
those used for driving steel sheet piles. However, pre-
(4) The backfill should be placed continuously as
cautions should be taken in handling and driving sheet
the trench is advanced. By so doing, sloughing of the
piling to ensure that the interlocks are tight for the
trench walls will be minimized, and the amount of ben-
full depth of the piling and that all of the sheets are
tonitic slurry required kept to a minimum. The level of
driven into the underlying impermeable stratum at all
the slurry in the trench should be maintained at least 5
locations along the sheet pile cutoff. Methods and
techniques for driving steel sheet piling are described
en to control the density and viscosity of the bentoni-
in numerous references on this subject.
tic slurry as required by the design. To minimize wast-
age of bentonitic slurry, it may be necessary to screen
d. Freezing. Freezing the soil around a shaft or tun-
out sand and gravel in order to reuse the slurry. (Con-
nel requires the installation of pipes into the soil and
struction techniques are still being developed.)
circulating chilled brine through them. These pipes
(5) The toe of the backfill slope should be kept
generally consist of a 2-inch inflow pipe placed in a
within 50 to 150 feet of the leading edge of the trench
6-inch closed-end "freezing" pipe installed in the
to minimize the open length of the slurry-supported
ground by any convenient drilling means. Two headers
trench. During placement operations, excavation and
are required for a freezing installation: one to carry
cleaning operations proceed simultaneously ahead of
chilled brine from the refrigeration plant and the oth-
the advancing backfill. (It should be noted that be-
er to carry the return flow of refrigerant. The refriger-
cause of the geometric constraints set by the backfill
ation plant should be of adequate capacity and should
slope, the amount of open trench length supported by
include standby or auxiliary equipment to maintain a
slurry is a function of the depth of the trench. For ex-
continuous operation.
ample, if the trench is 100 feet deep and the backfill
slope is 1V on 8H, the open length will be about 900 to
5-6. Piezometers.
950 feet-800 feet along the slope of the backfill face
a. Installation. Piezometers are installed to deter-
plus 100 to 150 feet from the backfill toe to the lead-
ing edge of the trench.)
or artesian) for designing and evaluating the perfor-
(6) When the trench is complete and the backfill
mance of a dewatering system. For most dewatering
occupies the entire trench, a compacted clay cap is nor-
applications, commercial wellpoints or small screens
mally placed over the trench. Key steps in this con-
are satisfactory as piezometers. The selection of well-
struction sequence involve the mixing of the bento-
point or screen, slot size, need for filter, and method of
nite-water slurry, excavation and stabilization of the
installation is the same for piezometers as for dewater-
trench, cleaning of the slurry, mixing of the soil-bento-
ing wellpoints. Holes for the installation of piezomet-
nite backfill, displacement of the slurry by the back-
ers can be advanced using continuous flight auger with
fill, and treatment of the top of the trench. Each of
a hollow stem plugged at the bottom with a removable
these items must be covered in the specifications.
U.S. Army Corps of Engineers
Figure 5-4. Installation of a slurry cutoff trench.
5-6