pavements. Graphs and formulae shall be clearly indicated along with the
derivation of curve slopes and data derived from the laboratory testing.
10-1.7
Drawings.
General guidance for preparation of Drawings is provided in Chapter 4, "Drawings" and
Chapter 7, "Electronic Design Deliverables."
In addition, include subsurface investigation results on the drawings for record-keeping
purposes. As a minimum, the drawings shall include the logs as they appear in the
Geotechnical Report, a summary table of the laboratory testing, notes concerning the
preparation notes or details, such as undercutting and surcharging.
10-1.8
Specifications.
General guidance for preparation of Specifications is provided in Chapter 5,
"Specifications" and Chapter 7, "Electronic Design Deliverables."
10-1.9
RFP.
General guidance for preparation of RFP is also provided in Chapter 3, "Development of
Design-Build Request for Proposal (RFP)" and Chapter 7, "Electronic Design
Deliverables."
10-1.10
Furniture, Fixtures, & Equipment (FF&E).
Refer to UFC 3-120-10, Interior Design, for additional guidance on FF&E package
development and submittals at each stage of design. Generally, the FF&E is included
with the Architectural submittals outlined in each design stage.
10-1.11
Critical Path Submittals.
Contractor submittals in Design-Build may be designated as Critical Path Submittals, as
further described in UFGS 01 33 10.05 20 (01331) of the RFP. In this situation, the
submittal may only contain the design of one or a few disciplines, for example, civil and
structural. Follow the submittal requirements as applicable for the disciplines pertaining
to that critical path submittal. Ensure that work is included and coordinated with the
other disciplines that are affected by that critical path work; for example, electrical and
mechanical site work is included and shown on the civil site work critical path submittal,
and provisions are made for the utility service entrances through foundation and for
major pieces of equipment for the foundation work critical path submittal.
10-2
CONCEPT DESIGN SUBMITTALS (10%-15%).