required. Discuss earthwork associated with foundation design and construction or site
improvements, including settlement, liquefiable soils, expansive soils, slope instabilities
or near surface groundwater. The discussion should address existing conditions,
studies, or analysis performed, and recommendations for mitigation of the effects of
these conditions. Address dewatering, and sheeting/shoring considerations, in design
and construction, as applicable. If required by the Designer of Record, state the
pavement design parameters and the pavement design. If the pavement design is to
be completed by others, provide design parameters determined from the subsurface
investigation. If multiple structures are being designed, address structures on an
individual basis. Discuss the site preparation and susceptibility to rain and construction
equipment. Discuss any soil conditions relating to potential concrete or piping
corrosion and recommendations to mitigate effects thereof.
For Design-Build projects, the submitted report shall be accompanied by a cover letter
from the DOR, identifying any recommendations of the report, proposed to be adopted
into the design, which are interpreted by the Contractor as either conflicting with or
being modifications to the Geotechnical or Pavement related requirements of the RFP.
9-2
REQUIREMENTS AND MANAGEMENT PLAN (RAMP).
For Air Force projects only, the RAMP provides project planning information such as
base architectural guidelines; base standards and regulations for fire protection, safety,
and other base or site specific requirements, such as a Base Long Range Plan. The
RAMP is prepared at the project base or major command level, and is provided to the
DOR by the Government's PM.