UFC 1-300-02
September 2004
Change 4 December 2006
<ITM INDENT=0.33>1. Item</ITM>
</SPT=1.1.1.1></SPT=1.1.1></SPT=1.1> /4/
Do not use progression beyond this level.
The SpecsIntact Quick Start Guide gives instructions for how to tag paragraphs using
the SpecsIntact software.
PART 1 GENERAL
1.1 REFERENCES
This paragraph is used to list the publications cited in the text of the guide specification.
The publications are referred to in the text by basic designation only and listed in this
paragraph by organization, designation, date, and title.
1.2 UNIT PRICES
Measurement and payment requirements will be specified for work subject to extreme
variation in estimated quantity when unit price bidding is required. This paragraph is not
used for guide specifications covering building components or for other construction
features when quantities can be reasonably calculated from information included in the
contract.
1.3 SYSTEM DESCRIPTION
This paragraph will be limited to statements describing performance or design
requirements and tolerances of a complete system. Limit descriptions to composite and
operational properties to the extent necessary to link multiple components of a system
together, and to interface with other systems.
1.3.1 Design Requirements
Design requirements may include criteria for structural, thermal, acoustical, or other
properties. Tolerances should be stated here only as they apply to the performance of
the complete system. Include tolerances of fabrication and installation in their
respective paragraphs under Part 1.
1.3.2 Performance Requirements
Performance requirements may include criteria for structural, thermal, acoustical, or
other properties. Tolerances should be stated here only as they apply to the
performance of the complete system. Include tolerances of fabrication and installation
in their respective paragraphs under Part 2.
10