UFC 1-300-02
September 2004
Change 4 December 2006
1.6 DELIVERY, STORAGE, AND HANDLING
This paragraph includes the necessary requirements on packing and shipping,
acceptance at site, and storage and protection.
1.7 PROJECT/SITE CONDITIONS
1.7.1 Environmental Requirements
This paragraph establishes any physical or environmental limitations or criteria. Such
conditions might include temperature, weather, humidity, ventilation, and illumination
required for proper installation or application.
1.7.2 Existing Conditions
This paragraph includes statements or references to documents where information may
be found pertaining to such items as existing structures or geophysical reports.
1.8 SEQUENCING AND SCHEDULING
This paragraph includes any special sequencing and scheduling required.
1.9 WARRANTY
This paragraph describes special or extended (more than one year) warranty or bond
covering the conformance and performance of the work of the section. A thorough
understanding of warranties is necessary to develop this paragraph.
1.10 MAINTENANCE
1.10.1 Extra Materials
This paragraph covers items to be furnished to the Government by the Contractor for
future maintenance and repair. Include items that might be difficult to obtain because of
color or pattern match, or spare parts needed to ensure continued operation of critical
equipment. Specifications should identify the items, state the quantities required, and
indicate to whom, when, and where items are to be delivered.
1.10.2 Maintenance Service
This paragraph covers provisions for maintenance service as applicable to critical
systems, equipment, and landscaping.
PART 2 PRODUCTS
2.1 MATERIALS
This paragraph describes the material to be furnished. Materials specified here are
generally those that are independently incorporated into the work under PART 3
12