UFC 3-260-11FA
25 May 2005
1.22.4
Contractor-Furnished Materials and Equipment
The D-B Contractor shall furnish all materials and equipment
necessary for a complete operable system that is not furnished by
the Government.
1.22.5
Testing
Before acceptance of the Aircraft Arresting System by the
Government,
the
D-B
Contractor
shall
simulate
aircraft
engagements and make any adjustments necessary to assure the
system is in operable condition.
- End of Section -
01016 - 25