8-1.4.7
National Capitol Planning Commission (NCPC), Commission of Fine
Arts (CFA) and State Historic Preservation Officer (SHPO) Review.
The Government will lead and coordinate all reviews and presentations to the NCPC,
the CFA, and SHPO. The Contractor shall provide the submission for the Government
to obtain approval from these agencies. The NCPC approval process typically spans 1
to 3 months of time with additional time for four public meetings on large projects.
The typical NCPC submission package includes the following information:
Vicinity Map
Site Map
Landscape Plan
Floor Plan
Elevations
Building Sections
Roof Plan
Storm Water Management Plan
Provide the above submission information in the following formats:
Six sets of architectural drawings (half sizes acceptable)
One set of presentation drawings rendered in color mounted on boards
Three sets of 8 x 11" (page size) black and white drawings
Photographs of the existing site conditions annotated to identify and locate
the contents
Samples of building finishes, catalog cuts, and other material samples
A Project Data Report in electronic medium. The Government will supply
the outline for this item; typically, one to three pages in length.
8-1.4.8
Local Design Reviews.
Local design reviews are required. Local approval may also be required. Consult the
Project Manager or Design Manager for the design activity administering the design.
8-2
FINAL GOVERNMENT APPROVAL.
Authority and responsibility for formal approval of drawings and specifications and RFPs
by or for the Commander, NAVFAC, is vested in the Facility Engineering Command,
Chief Engineer and their delegated signatory representative(s). The level of approval