UFC 1 -300-08
30 JUNE 2004
not be an engineer, an engineer should first make a determination of quality workmanship
and that the facility(ies) is/are physically complete and available for use or beneficial
occupancy. This determination is normally made on the basis of an inspection where the
construction contractor is present. Upon successful inspection, the engineer project
manager accepts the construction from a contractor on behalf of the government using
contract procedures. However, the DD Form 1354 deals with the transfer and acceptance
of accountability for real property. Therefore the facility transfer inspection in this UFC
refers to a meeting event involving the construction agent project manager (or losing
accountable officer for transfers of existing facilities) and the gaining RPAO to transfer
accountability for a facility(ies). The gaining RPAO should exchange his/her Accepted By
signature on the DD Form 1354 for permission to occupy the facility, often signified by the
passing of keys.
1-8
USAGES AND PURPOSES OF DD FORMS 1354. The DD Form 1354,
Transfer and Acceptance of Military Real Property, is used to record transfers, changes,
additions or deletions of real property owned by the Military Services. The DD Form 1354
is used for a diverse number of real property transactions, which are listed.
1-8.1
Transfer accountability for new construction and/or capitalization projects from
the construction agent (e.g., USACE District/NAVFAC Division) to the installation RPAO.
1-8.2
Transfer accountability for new construction and/or capitalization projects from
the installation DPW/FacMgr/BCE/DIS project manager to the installation RPAO.
1-8.3
Transfer and accept accountability of real property (land and other facilities)
acquired on behalf of an installation from the private sector, other military services or other
Federal agencies by acquisition or grant.
1-8.4
Transfer and accept administrative accountability of real property from tenant
organizations to installation RPAO, e.g., from DLA, DeCA, ARMS, and Energy Savings
Performance Contractors; for real property accountability purposes only. Control remains
with the funding organization.
1-8.5
Transfer real property accountability for usable research and development
structures at the end of the research project.
1-8.6
Reassign accountability of real property between services, commands, and
installations.
1-8.7
Document the total cost of a new facility or a capital improvement in the
installation's real property database.
1-8.8
Document disposals of real property.
1-8.9
Document real estate transactions, e.g., purchases, sales, leases, licenses, and
permits.
1-8.10
Document adjustments caused by damage to real property in the real property
records.
1-8.11
Document real property accountability changes to make the real property
database agree with physical inventory results, e.g., found on post.