completion of the project requires that the contractor have sufficient technical UMCS personnel to
complete the tasks within the designated schedule and that the Government perform its functions in a
timely manner. The length of a construction period for a typical UMCS from notice to proceed to system
acceptance is estimated to be: 320 days (base effort) plus (0.18 calendar days times the number of
points) plus (1.75 calendar days times the number of smart field panels).