UFC 3-300-10N
May 2005
Including Change 2, August 2006
2-2.11.2
The structural construction documents must include the following:
a. Complete dimensional information as required to design the system or
component part
b. The nature, location, and magnitude of all design loads to be imposed on
the structure
c. All design criteria for both the overall structure and the system or
component part to be designed by the delegated engineer
d. All serviceability limit states that apply to the system or component part to
be designed by the delegated engineer
2-2.11.3
The delegated engineering submittals must include the following:
a. Identification of the project
b. A printed title block bearing the printed name, address, license number of
the delegated engineer, and the date of the drawing
c. The seal and signature of the delegated engineer
d. Installation or erection drawings, showing full details of materials to be
used, including necessary accessories and instructions for construction,
component details, and connection details
e. Calculations, showing all loads and other design criteria, and the
magnitude and location of loads and reactions on other portions of the
structural system
2-2.11.4
The structural engineer of record must review all submittals to verify
compliance with the design intent and the specified design criteria, and to ensure
coordination with the contract documents and other shop drawings. All submittals from
the delegated engineer must be approved prior to the start of fabrication of the system
or component part, and prior to any field construction that may be affected by the
system or component part.
2-2.11.5
The following submittals do not require the seal of a professional engineer:
a. Drawings prepared solely to serve as a guide for fabrication and
installation and requiring no engineering input such as reinforcing steel
shop drawings, structural steel, and steel joist and joist girder erection
drawings.
b. Catalog information on standard products not fabricated for a specific
project.
9