5.1
GENERAL. All drawings, both Government- and Contractor-furnished,
shall be prepared in an electronic format selected by the project owner. Appendix
01018-B of Section 01018, Design After Award for Airfield Contracts (Appendix K),. is a
suggested outline for both Government- and Contractor-prepared drawings. The RFP
preparer should edit Appendix 01018-B to meet the requirements of the project.
5.2
GOVERNMENT-FURNISHED DRAWINGS. Paragraph 2-5 provides a
suggested list of drawings to be included in the RFP. Drawings should be provided in
both hard copy and electronic format. The D-B Contractor can then use these drawings
to further the design and include in the final documents. Government-prepared drawings
should conform to the guidelines in Appendix 01018-B where applicable.
5.3
CONTRACTOR-FURNISHED DRAWINGS. The Contractor should be
required to develop a complete set of project construction drawings in conformance with
the suggested drawing list in Appendix 01018-B. The Contractor will be required to
furnish some drawings with the design analysis that will not be included in the
construction plans, such as obstruction profiles and drawings needed to support the
design development. These design analysis drawings should be in the same size and
format as the construction drawings.
46