Table 16 (Continued)
Solid Waste Landfill Design Checklist
Step
Task
3 Design filling area
a. Select landfilling method based on:
(1) Site topography and slopes
(2) Site soils
(3) Site bedrock
b. Specify design dimensions
(1) Trench width, depth, length
(2) Cell size
(3) Cell configuration
(4) Trench spacing
(5) Fill depth
(6) Interim cover soil thickness
(7) Final cover soil thickness
c. Specify operational features
(1) Use of cover soil
(2) Method of cover application
(3) Need for imported soil
(4) Equipment requirements
4 Design facilities
a.
Leachate controls
b.
Gas controls
c.
Surface water controls
d.
Access roads
e.
Special working areas
f.
Structures
g.
Utilities
h.
Fencing
i.
Lighting
j.
Washracks
k.
Monitoring wells
l.
Landscaping
5 Prepare design package
a.
Develop preliminary site plan of fill areas
b.
Develop landfill contour plans
5.10-69