TM 5-803-1
for construction. Should major, irreconcilable adverse
5-4. Use of the assessment.
The EA process and appropriate findings will be documented environmental impacts be identified. the long-range plans
( Land Use Plan. Circulation Plan. or Utility Service
and included in the Master Plan Report The EA will
Plans) should be reviewed for possible revision prior to
continue to be used as a reference as the General Site
Plans are developed and as specific projects are scheduled incurring those impacts.
"'---