UFC 1-300-09N
25 May 2005
Change 1, 22 February 2006
Change 2, 4 December 2006
CHAPTER 12 POST-CONSTRUCTION DOCUMENTS
12-1
PROJECT CLOSE-OUT
The Designer of Record (DOR) may be required to execute specific project tasks during
project close-out. These tasks may include preparing DD Form 1354, "Real Property
Record," for Government signature, attending project close-out meetings, or performing
other tasks. Refer to the design contract (if a Design-Bid-Build project) or the Design-
Build RFP for project close-out related tasks.
12-2
RECORD DESIGN
The Record Design documents are comprised of the Final Design documents inclusive
of marked prints (As-Built Marked Prints) indicating construction deviations from the
Final Design Contract Documents. Prepare in accordance with paragraph 7-3.6.
76