CEMP-E
TI 800-03
1 July 1998
Construction phasing (schedule of critical dates, allowed utility outages, security, times Design-Build
Contractor is allowed to work in certain areas and other government restraints.)
Drawings/specifications of existing building if project is renovation or expansion.
Evaluation and selection criteria weighted matrix.
Exterior signage requirements.
Site
Site Location/Zoning Analysis.
Geotechnical Report (include soils test analysis, permeability, CBR, site preparation
requirements, and foundations requirements).
Site and Topographical Surveys (includes property lines, utility locations, easements, set-
backs, all structures above and below grade, trees, wetlands, environmentally-protected areas,
streets, roads, etc.). Provide finish contours as needed and required for completion of design
by the Design-Build Contractor.
NOTE: The Corps should ensure that the site and topographical surveys and all other existing
conditions provided to the Design-Build Contractor are accurate. The installation and other
organizations should not be permitted to provide site and topographical surveys, and other
information/conditions, directly to the Design-Build Contractor without verification. The Design-
Build Contractor must be required to verify all site and topographical surveys and other existing
conditions. The Corps should take extra precautions to ensure that the Design-Build
Contractor verifies the site and topographical surveys, and other information/conditions, prior
to beginning any work. These requirements should be made explicit in the RFP.
On-base borrow pits and spoil areas that the Design-Build Contractor may use during his
Contract.
Water pressure and flow test.
Utility tie in points.
Stormwater Management System description.
Demolition drawings
Volume and traffic composition, so Design-Build Contractor can determine pavement thickness
and structure.
Identify conceptual Landscaping, Planting and Turfing requirements. Describe existing site
conditions, including indication of existing plant material that is to remain. Include a list of
suggested types and minimum sizes of plant materials which are to be used. Indicate specific
plant locations if specific plants are required by Customer or special site problems.
B-2