CEMP-E
TI 800-03
1 July 1998
APPENDIX B
EXAMPLE TECHNICAL PROJECT CRITERIA TO BE PROVIDED
BY THE GOVERNMENT IN RFP's
General
Offeror response requirements, elements/format.
General project description or mission statement addressing Government prioritized issues such as:
Project size
Time critical construction completion requirements
Sustainable (permanence, quality)
Image - "High" Profile (major urban facility) vs. "Low" Profile (infill, industrial park)
Cost effectiveness
Aesthetics and historical context (if appropriate)
"Green design" environmentally-friendly
Site complexity
Future expansion parameters
Project specific design criteria including required guidelines, standard details, handicapped elements,
security, etc., and all special or unusual criteria requirements believed to have a significant impact on
the facility above those in a typical facility of same type.
List of Government-Furnished/Government-Installed Furniture and Equipment. Indicate the Design-
Build's contractor's responsibilities for the equipment (comp. air, power, water, structural support,
clearances etc.).
List of Government-Furnished/Design-Build Contractor-Installed Furniture and Equipment. Indicate the
Design-Build's contractor's responsibilities for the equipment (comp. air, power, water, structural
support, clearances etc.).
List of Design-Build Contractor-Furnished/Contractor Installed Equipment.
Agreements and jurisdictional constraints (with local utilities, site restrictions, permits obtained/needed
and contacts on above.)
Environmental issues including impact statement/assessment, special investigations, any agreements
or permits with other agencies and mitigation work.
Asbestos and lead paint reports. Identify who is responsible (the Government or the Design-Build
Contractor) for removal of asbestos or lead paint.
Outline specifications briefly describing performance and quality for all disciplines.
B-1