UFC 3-260-11FA
25 May 2005
a.
Location and Sequencing of Work Areas
b.
Scheduling for Each Phase of Project
c.
General Listing of Tasks to be Performed Under Each Phase
d.
Concurrent Construction That May Affect Each Phase
e.
Location and Type of Area Control (Security) Measures
1)
Temporary Barricades and Fencing
2)
Temporary Lighting
3)
Temporary Pavement Markings (Closure Markings)
f.
Traffic Circulation (Aircraft and Vehicular)
g.
Special Notes
1)
Security Measures
2)
Contractor's Housekeeping Measures
3)
Controls on Contractor's Traffic
8.
HORIZONTAL AND VERTICAL CONTROLS
a.
Layout
b.
Bench Marks (USGS Datum) With Only One Master Bench Mark
c.
Control Stationing
d.
9.
GEOMETRIC LAYOUT PLAN (OPTIONAL)
a.
Curve Data
b.
Control Stationing
c.
Geometric Layout
10.
BORING LOCATION PLAN AND BORING LOG DATA
11.
PAVEMENT REMOVAL PLAN
a.
Pavement Removal Limits (e.g., Dimensions, Stationing)
b.
Type and Thickness of Pavement Removed
c.
Utilities and Structures Affected by the Removal
1)
Manholes
2)
Aircraft Arresting System
3)
Blast Deflectors
4)
Runway/Taxiway Lighting
5)
Communication Cables
6)
Water/Sewer Lines
7)
In-Ground Aircraft Support Systems
d.
Special Notes Regarding Removals
e.
Location of Removal Sections
12.
REMOVAL SECTIONS AND DETAILS
Sections should be specific, not general or typical. Show several
sections. Show new sections for changes in pavement type, thickness, or
any other condition that has an impact on pavement construction.
Sections should be complete both laterally and vertically for the
entire pavement structure, including subgrade preparation.
01018B - 2