EI 11C201
CEMP-E
1 March 1997
systems. Due to its weight concrete pipe minimizes but may not eliminate the need to be anchored to
prevent floating.
g. Design guidance. The methods and procedures described in WEF Manual of Practice No.
9 for designing sewer installations in unsatisfactory soil, rock, embankments, microtunneling, and
by tunneling, microtunneling, jacking, boring, etc., will be adopted. Sewer piping installed in
areas subject to earthquake damage will include seismic design as required by TM
5-809-10/AFM 88-3, chapter 13. Cold region facilities will be designed in accordance with TM
5-852-5.
5-12