MIL-HDBK-1005/16
(6) Wellheads and associated piping are modified
to allow for bi-directional versus single direction flow. Note
that with ASR, plugging issues are of less concern since the ASR
well is periodically pumped as part of the normal operation.
b) In determining whether to design a disposal system
or ASR system, many predesign criteria should be evaluated.
These generally include, as a minimum, the following criteria:
(1) Analysis of reclaimed water supply and demand
(2) Characterization of reclaimed water quality
and native formation water quality
(3)
the area
(4) Compatibility of and recovery efficiency of
reclaimed water stored for reuse applications
(5) Identification of suitable storage or
disposal hydrogeologic sequences
6() Permitting considerations to determine which
program meets the environmental objectives and standards set for
the area
167