Review process for claiming under warranty. Verify that the warranty's procedure for
creating a warranty claim is reasonable and alert the building user to the procedures.
D-6
CLOSE-OUT.
Warranty information needs to be provided to the building user during the project close-
out phase.
D-7
BUILDING MAINTENANCE.
Building maintenance is one of the keys to maintaining the warranty. Contracts can
include prepaid yearly inspections to comply with manufacturer's requirements for
keeping the warranty in effect.