UFC 1-300-09N
25 May 2005
Change 1, 22 February 2006
Change 2, 4 December 2006
the direction of a Registered Architect or a Professional Engineer currently licensed by a
United States state, commonwealth, or territory, the District of Columbia, or by the
foreign country in which the project is to be built.
Each drawing shall only be signed, sealed, and dated by the Registered Architect or the
Professional Engineer who is registered to practice in the particular field involved for
work depicted on that drawing, serves as the Designer of Record for that work, and
complies with requirements of FAR 52.236-26. Sign Record Documents in accordance
with Electronic Design Deliverable requirements.
2-6.1
Certification.
Where special certifications are required for the design, certify in accordance with the
contract and local requirements.
5